Case Study / Hospitality

Hampton by Hilton,
Liverpool John Lennon Airport

Plantroom Remediation
Project Value £65k
July 2024 – March 2026
Project Overview

Vital Synergy was engaged as engineering partner to address cascading failures in the domestic hot water generation and cold-water pressure control systems at this busy airport hotel. What began with a calorifier upgrade in 2024 escalated through two critical failure events, a PRV burst causing internal flooding and a subsequent cylinder pin-hole leak, into a holistic plantroom remediation programme covering calorifier replacement, water softening, PRV renewal across all risers, and a full booster pump upgrade to variable-speed control. All works were commissioned in March 2026 with a structured handover to the hotel engineering team.

Client and Sector

Client Overview

Client Hampton by Hilton, Liverpool John Lennon Airport

A busy airport hotel in Speke, Liverpool (L24 1YD) where uninterrupted hot water supply is critical to guest satisfaction. Vital Synergy was engaged as engineering partner following recurring failures in the domestic hot water generation and cold-water pressure distribution systems, with a mandate to investigate root causes and deliver a lasting remediation.

Sector Hospitality / Hotels

Delivering remediation within a live, occupied hotel placed specific demands on programme sequencing and risk management. All interventions were planned riser by riser to minimise outages to guest floors, with planned shutdowns agreed in advance with Chief Engineer Phil Griffiths and the hotel management team. Site-specific Risk Assessments and Method Statements were issued and approved before each phase of works.

Scope of Works
Phase 1: Calorifier Installation (2024)

Four new 749 L storage calorifiers installed on 12 July 2024, boosting hot water capacity and modernising the ageing plant. System chlorination and full handover documentation completed at the close of Phase 1, providing a documented baseline for the newly upgraded hot water generation system.

PRV Replacement Programme

Full replacement of pressure reducing valves across all risers with heavy-duty Caleffi 536-series PRVs rated for approximately 8 bar inlet pressure. New full-bore isolation valves fitted in place of old service valves. Each riser drained, re-pressurised and verified under live flow at bedroom fixtures to confirm balanced pressure throughout all storeys.

Booster Pump System Upgrade

Fixed-speed booster set converted to variable-speed operation with new inverter controls and a correctly sized pressure expansion vessel, replacing the inadequate 60 L original. New control logic rotates pump duty for even wear and dual redundancy, eliminating water hammer pressure transients and protecting the new PRVs from surge damage.

Hot Water System Remediation

Cylinder No.1 replaced under manufacturer's warranty approval, restoring full four-cylinder operation. Water softener installed on the building's incoming supply to treat all makeup water feeding the calorifiers. Cylinders No.2, 3 and 4 cleaned and fitted with new sacrificial anodes. Comprehensive re-commissioning and chlorination of hot and cold-water circuits performed at handover.

Results

Key Outcomes and Benefits

4 Calorifiers Fully Reinstated

All four 749 L storage vessels returned to full service, eliminating the capacity shortfall caused by the Cylinder No.1 failure and restoring complete domestic hot water redundancy across the hotel.

11 Defects Documented

Senior engineers documented 11 distinct defects with photographic evidence during the 6 November 2025 inspection, providing the evidence base for both the warranty claim and the wider remediation scope.

749 L Per Vessel Capacity

Four calorifiers providing a combined 2,996 L of hot water storage, providing a resilient platform for the hotel's operational demands, sized to cope with peak occupancy without risk of supply shortfall.

Zero Pressure Incidents Post-Upgrade

Variable-speed booster controls and new Caleffi PRVs have delivered stable cold-water pressures with no further over-pressurisation or valve failure events recorded since commissioning in March 2026.

On Time Delivered to Programme

All Phase 2 remediation works completed and commissioned by March 2026 in line with the agreed programme, with no unplanned disruption to hotel operations or guest experience throughout.

12 Mo. Defects Liability Coverage

A 12-month defects liability period applies to all remediation works, providing the client with contractual assurance over the long-term performance of the upgraded plantroom infrastructure.

Investigation, Compliance and Delivery

Project Detail

The Hampton by Hilton at Liverpool John Lennon Airport presented a complex, multi-phase remediation challenge. Two critical failure events, a PRV burst in late 2023 causing internal flooding and a hot water cylinder pin-hole leak in November 2025, exposed underlying vulnerabilities in both the pressure control and hot water generation systems. Vital Synergy was engaged to investigate root causes and deliver a structured remediation that would address those causes directly, rather than treating symptoms alone.

All works were delivered within a live, occupied hotel environment. Programme sequencing was agreed riser by riser with Chief Engineer Phil Griffiths, isolating only one riser of guest rooms at a time and scheduling interventions during low-occupancy periods to limit disruption to guests throughout.

Root Cause Analysis and Investigation

A detailed technical investigation was carried out on 6 November 2025. Senior engineers performed full internal and external inspections of all four hot water vessels and documented 11 distinct defects with photographic evidence. Cylinder No.1 was found to be severely degraded internally by limescale deposits and corrosion, particularly around the cold-feed inlet and inspection flange. Its sacrificial anode had not been replaced since commissioning and was almost completely consumed; manufacturer guidelines call for six-month inspections and annual anode replacement, neither of which had occurred during 16 months of operation.

Root cause of the calorifier's premature failure was confirmed as hard water chemistry (site supply classified "slightly hard" per United Utilities data, trending towards moderately hard) combined with a lack of routine maintenance. Cylinder No.1 was deemed beyond economical repair and taken out of service. A parallel review of the cold-water booster and PRV system found that the existing Wolseley "Jet" type PN16 PRVs were inadequate for the booster's fixed-speed operating regime. Pressure transients (water hammer) produced by constant-output pumping, combined with an undersized 60 L expansion vessel and an absence of surge suppression, had overstressed the PRVs and likely precipitated the burst flooding event. Upstream static pressures were measured at approximately 8 bar.

Programme and Delivery

Phase 1, completed in July 2024, installed four new 749 L storage calorifiers with full system chlorination and handover documentation, addressing the immediate hot water capacity shortfall. Following the November 2025 failure, immediate containment isolated Cylinder No.1 and pre-emptively replaced the anode on Cylinder No.2, restoring supply continuity from the remaining three vessels whilst the warranty claim and wider remediation were progressed.

Phase 2 remediation works were tendered in early 2024 and commissioned in March 2026. PRV replacement was delivered across all risers with full-bore isolation valves, tested and verified under live flow. The booster set was retrofitted with modern inverter controls and a correctly sized expansion vessel. Cylinder No.1 was replaced under the manufacturer's warranty; the remaining cylinders were cleaned, re-anoded and re-insulated. A water softener was installed on the building's incoming supply. Comprehensive RAMS were issued and adhered to per phase. The structured handover package provided to the client's engineering team included updated as-fitted documentation, operation manuals for the new control systems, and water treatment maintenance guidelines.

The plantroom remediation carried out by Vital Synergy has restored our mechanical plant to full performance and given us complete peace of mind. Their team worked around our live hotel operation with minimal disruption to guests, and the results have exceeded our expectations.

Hampton by Hilton, Liverpool John Lennon Airport

Hospitality Plantroom Remediation Calorifiers PRV Replacement Booster Pumps Liverpool
Connect